After completing the remediation work and the diversion of the Keelbeekpad, the earthworks will also start in the zone between Witloofstraat and the present Keelbeekpad.
At the end of January 2019, drilling of the first foundation piles will begin. Soil-displacing screw piles will be used. The advantage of this method is that no vibrations are caused and no extra soil needs to be removed, eliminating the need for some 600 transports.